PROGRESSIVE ENGINEERING COONSITE PRECAST CONCRETE SOLUTIONS Request Project Assessment
Home › Insights › When Does an On-Site Precast Plant Make Economic Sense?
Insights

When does an on-site precast plant make economic sense?

An on-site plant is a fixed cost you pay once to save a little on every block afterwards. Whether that trade works depends on about a dozen things, most of which you can judge from the BOQ, a map and a site plan. Here is how we go through them.

Heavy kerb blocks fresh off the press at an on-site plant

Here is the whole economics of on-site precast in one sentence: you spend money once to set up production at the site, and in return you save some money on every unit you make there.

So the real question is never “is on-site cheaper?” It is “are there enough units, each saving enough, to cover the setup with room to spare?” These are the factors we look at on every enquiry, roughly in the order they matter.

1. Project quantity

Setup cost does not care whether you make one lakh blocks or eighty lakh. Spread over a small quantity it swamps any saving; spread over a large one it almost disappears. At Dhamra Port the scope was 2,50,000 square metres of pavers, about 80 lakh blocks. At that scale the question was never whether to produce at site, only how.

2. Distance from a conventional precast supplier

Every kilometre between a factory and your site adds freight to every unit. Close to an established plant, that number is small and the factory usually wins. At a port under construction, a power plant in a remote district or a new region, the saving on every unit becomes substantial.

3. Transportation

Concrete is heavy and cheap per kilo, which is a bad combination for trucking. Heavier units mean fewer pieces per truck and more trips. The kerbs we made at NTPC Sipat were 500 × 300 × 250 mm, about 110 kg each. When we once had to arrange trucks for 5,000 tonnes of paver blocks from Leh to the Sasoma checkpost in Ladakh, freight stopped being a line in the estimate and became a project of its own.

4. Loading and unloading

A block from a distant factory is lifted, stacked, loaded, unloaded and restacked before it reaches the work front. Each of those handlings costs labour and time. Made at site, the journey is short: press, curing, stack, work front.

5. Breakage and damage

Every handling is a chance for a chipped edge or a broken corner. A few percent sounds small until it is multiplied across lakhs of units, and then argued over with a supplier. Fewer handlings means fewer rejects and fewer disputes.

6. Production duration

A plant that runs for months keeps saving after its setup is paid off; a two-week job gives it no time. Dhamra’s production ran for 12 months. The road-shoulder works at NTPC Sipat ran for 15 months and covered kerbs, pigmented pavers and 50 lakh fly ash bricks, all manufactured by us.

7. Site availability

An on-site unit needs a level, well-drained plot for raw materials, production, curing and finished stock, close to the work. If the site genuinely has no room, the case weakens quickly. How much space an on-site unit needs explains how to size it.

8. Raw material availability

Production still needs cement, sand, aggregate and, where the mix calls for it, fly ash. Usable local sand and aggregate strengthen the case. Sand quality varies between regions, so the mix is designed around what is actually available and approved before regular production.

9. Plant mobilisation

Bringing in the press, moulds, batching, mixing and curing arrangements, installing and commissioning them, and later demobilising, is the main fixed cost. It is also time: production does not start on day one, and the programme has to allow for it.

10. Manpower

A site plant needs trained operators, supervisors and production crews, and on a remote site they have to live near it. Our core team has been with us for many years; on-site production only works if the people running it can solve problems without waiting for someone from the city.

11. Curing space

Fresh blocks need days of curing before they can move, so the curing area has to hold several days of production at once. It is usually the curing and stacking yard, not the machine, that decides the plot size.

12. Production capacity

The plant has to match the laying rate, not the other way round. Our capacity is 15 lakh+ blocks a month, and 25,000 chequered tiles a day. The configuration for a particular site is sized from its quantities and programme.

13. Project schedule

Production has to run ahead of laying by at least the curing period, plus a buffer. A tight programme can still work with site production, but it changes how big the plant has to be. Plan backwards from the laying programme, as described in how to plan precast production for a large project.

14. Logistics constraints

Remote roads, security restrictions at ports and plants, monsoon and cyclone seasons: anything that makes regular truck deliveries unreliable pushes the answer towards producing at site. At Dhamra the weather flooded our production area more than once; the job was completed anyway, which is exactly why the plant had to be there.

Putting numbers to it

Every rupee figure in this section is a made-up round number to show the arithmetic. None of them are our rates or anyone’s market price. Plug in your own.

Landed cost of buying = factory price + freight per unit + loading and unloading + allowance for breakage and rejects
Saving per unit = landed cost of buying − variable cost of producing at site
Break-even quantity = one-time setup and demobilisation cost ÷ saving per unit

If the saving per unit is zero or negative, stop: on-site does not make sense at any quantity. Otherwise, say buying lands at ₹60 a paver and making it at site costs ₹52 in variable cost: the saving is ₹8. With a setup and demobilisation cost of ₹24 lakh, break-even is 24,00,000 ÷ 8 = 3 lakh pavers. A project needing 15 lakh pavers saves ₹96 lakh on the 12 lakh beyond break-even; a project needing 2 lakh should buy them.

Notice how sensitive this is to distance: push the site further from the factory and the landed cost rises, the saving grows and the break-even falls fast. That is why remote projects are where on-site production shines.

When it does not make sense

We would not recommend a site plant when the quantity is small, a good factory is close, the site has no space for production and curing, or the job will be over before the plant settles into rhythm. Buying finished product is the sensible choice then, and we will tell you so. The other side of the comparison is in on-site vs off-site precast manufacturing.

For a real answer you need real quotes, real freight rates and a real site plan. Send us your BOQ, location and schedule and we will work through it with you. How the operation itself is set up is on our on-site precast manufacturing page.

Angadh Ahluwalia is a partner at Progressive Engineering Co., Nagpur. The firm was founded in 1977 in civil engineering and has manufactured precast concrete since 2001, setting up production units at project sites across India.

Want this worked out for your project?

Send your BOQ, location and timeline. We will come back with a preliminary view, including when on-site does not make sense.