Dhamra Port, Odisha — 80 lakh heavy-duty pavers made on site for Adani Ports
The project
Dhamra is a working port on the Odisha coast, and the pavement it needed takes a beating every day: internal roads, truck parking, and a steel stackyard where heavy coils and plates are stored and moved. The specification was 80 mm unipaver blocks, 250 × 125 mm, M-50 grade, to BS 6717.
The area was about 2,50,000 square metres, which works out to 80 lakh blocks. We manufactured every one of them, supplied them to the work front and laid them with our own crews.
Why the plant had to be at the port
Eighty lakh blocks is a lot of trucks. Dhamra is a very remote location, far from any established precast factory, and the coast there sees extreme monsoons and frequent cyclones that make road supply unreliable. Buying finished blocks and hauling them in would have meant a long, fragile supply chain and heavy losses to handling.
So we set up our plant at the port. Production ran for 12 months, with the blocks moving a short distance from the curing yard to the areas being paved.
Testing to BS 6717
The blocks were tested as per BS 6717, under a QC plan agreed with the client before regular production started: what gets tested, how often, and what happens to a batch that does not pass. Settling that up front meant the arguments that usually come later did not come.
The finished pavement was then put through the vibratory roller test across the roads and the stackyard, which is about as direct a way to show a pavement’s strength as there is. It came through without cracking. More in what the vibratory roller test tells you about a paver.
Laying: herringbone at 45 degrees
Laying followed IRC:SP:63, in a herringbone pattern at 45°. Herringbone is the pattern that locks best under traffic that turns, brakes and accelerates, which is exactly what trucks and handling equipment do in a port. The blocks were laid to line and level, compacted, and the joints filled with jointing sand before each area was released.
The hard part: a remote site through the monsoon
Two things made Dhamra hard: distance, and weather. Everything from spares to cement had to be planned well ahead, and there were days when our production area stood under water, press and mixer included. A site plant in a place like this is only as good as the team’s ability to protect it, wait out the water, check it properly and start again. I have written more about that in what extreme weather teaches you about on-site precast.
From the site